Timeline
Pre-award
- May, 1994
- Preliminary planning with Hill House and CLP
- Network access for Hill House personnel
- Qualification of cable lines for school sites and PSC
- June, 1994
- Installation of lines for school sites and PSC
- Delivery of DEC servers for school sites
- Evaluation of DEC PC's
- July, 1994
- Shakedown of cable links for school sites
- Delivery of DEC PC's for school sites
- Setup of servers for school sites
- Planning for CLP online exhibit
- August, 1994
- Setup of PC's for school sites
- Installation of servers and PC's for school sites
- September, 1994
- Shakedown of equipment at school sites
- Verification of all matching funds indicated in the
present proposal
Post-award
- October, 1994
- Start of first semester activities at school sites
- Advertisement of job openings
- Selection of equipment for Mosaic Foundries
- Selection of connectivity options for CLP and Hill House
- Qualification of lines for CLP and Hill House, as needed
- Final specification of scope of CLP online exhibit
- Initial statement of project goals for Hill House
- November, 1994
- Final selection of project staff
- Definition of outreach program
- Installation of Mosaic Foundries at school sites
- Delivery of servers and PC's for Hill House and CLP
- Installation of network links for CLP and Hill House
- December, 1994
- Inservice training in the use of Mosaic Foundries
- Outreach activities for regional schools
- Initial scanning of images for CLP exhibit
- Shakedown of equipment at CLP and Hill House
January, 1995
- Outreach activities for local government
- Installation of equipment at seed sites
- Teacher in-service sessions for seed sites
- Planning of Hill House online services
- Initial online images from CLP
- Public access from CLP available
February, 1995
- Start of second semester classroom activities at school sites
- Outreach activities for local businesses
- Installation of Mosaic Foundry at Hill House
March, 1995
- Outreach activities for cultural institutions
- Public access available from Hill House
- Public services begin on Hill House server
April, 1995
- Conference on regional networking sponsored by CK:P
- Preparation of follow-on proposals
May, 1995
- Gathering of summary information for project activities
June, 1995
- Decision on options for continuing connectivity
July, 1995
- Shift to alternate connectivity modes, as needed
August, 1995
- Shakedown month for alternate connectivity
September, 1995
- Preparation of final report on project activities