This is a timeline for the migration of CK:P activities to PPS. It will be sent to all parties involved and consensus will be reached on responsibilities and deadlines.
Responsibility | Deadline | Task Accomplished | |
Modem Pool - test 8 lines and SLIP/PPP | Hastings and Taylor | March 1, 1996 | Done - March, 1996 |
Connectivity through Bellefield for Fort Pitt, McCleary, Spring Hill | Hastings and Taylor | April 1, 1996 | Done - April, 1996 |
Modem Pool Design Finalized and Equipment Ordered | Hastings and Taylor | April 30, 1996 | Done - May, 1996 |
Connectivity through Bellefield for LADS Sites (Schenley, Frick, Liberty) | Hastings and Taylor | June 1, 1996 | Done - October, 1997 |
Modem Pool - test at least 40 lines for home access with authentication via a PPS Terminal Server | Hastings and Taylor | June 30, 1996 | Done - October, 1996 |
Modem Pool Revisited, Upgraded, Refined | Hastings and Taylor | September, 1997 | Done - October, 1997 |
Modem Pool Software (Radius) Automated to Restrict Student Use | Berger, Becker, Rapier | September, 1997 | Done - October, 1997 |
Test of Interoperability of Cisco and Ascend routers | Hastings, Berger, Adams, Taylor | July 1, 1996 | Done - April, 1997 |
Connectivity through Bellefield for ISDN Sites (All the rest) | Hastings and Taylor | August 1, 1996 | Done - November, 1997 |
Modem Pool - Migrate home users off CMU & Pitt to PPS modem pool | CK:P Ed-staff | September 1, 1996 | Done - November, 1996 |
Network Equipment Owned by CMU Donated to PPS | Berger, Huntoon, Wertheimer, Miller, Lentz | March 1, 1997 | Done - November, 1997 |
Connectivity through Bellefield - 1996 New Sites | Hastings and Taylor | Fall, 1996 | Done - April, 1997 |
Connectivity through Bellefield - 1997 New Sites | Hastings and Taylor | Fall, 1997 | Pending |
Transfer of Connectivity Costs to Sites | Ed Staff | Fall, 1997 | Done - December, 1997 |
PPS Negotiates Connectivity to Internet | Myron Lentz | Fall, 1997 | Done - October, 1997 |
Responsible Party | Deadline | Task Accomplished | |
Configure CATS2 as the PPS information server. | Berger, Kern, Becker, Charnock, Taylor | July 1, 1996 | Done - December, 1997 |
Configure CATS1 as the PPS central account server. | Berger, Kern, Becker, Charnock, Taylor | August 1, 1996 | Done - May 1997 |
Decision on Operating System - NetBSD or BSDi | Berger, Kern, Becker, Charnock, Taylor, Lentz | June 1, 1996 | Done - May, 1996 |
Configure 1996 site servers | Berger, Kern, Becker, Charnock, Taylor | February, 1997 | Done - April, 1997 |
CATS1 is placed into production at PPS | Berger, Becker, Charnock, Taylor | January 1, 1997 - March 1, 1997 | Done - June 2, 1997 |
CATS2 is placed into production at PPS | Berger, Becker, Charnock, Taylor | March 1, 1997 | Done - December, 1997 |
Oberon and Titania are shut off - become backup machines. | Berger, Kern, Becker, Charnock, Taylor | March 1, 1997 | Done - December, 1997 |
Project Servers Owned by CMU Donated to PPS | Berger, Huntoon, Wertheimer, Miller, Lentz | March 1, 1997 | Pending |
PPS Configure 1997 site servers | Becker, Charnock, Taylor | September 1, 1997 | Pending |
Transfer Spring Hill Server to BSDI | Becker, Berger, Charnock | September 1, 1997 | Done - August 1997 |
Upgrade Site Servers to BSDI 3.0 | Becker, Charnock | September 1, 1997 | Pending |
User Devices
refers to the hardware and software configuration of a given user
device.
Responsible Party | Deadline | Task Accomplished | |
Setup MACS at third year sites | Miller, Zinga, Becker, Charnock, Taylor | March, 1996 | Done - March, 1997 |
Setup PCs at 3rd year sites | Miller, Wertheimer, Franklin, Check, Becker, Charnock, Taylor | April, 1996 | Done - April, 1997 |
WFWG - PC-Remote-Build - Old sites | Miller, Wertheimer, Adams, Berger | May 1, 1996 | Done - May, 1996 |
Win95 - Production Setup | Rapier,Miller, Check, Berger, Wertheimer, Becker, Charnock, Taylor | July 1, 1996 | Done - September, 1996 |
MAC Production Setup | Miller, Zinga, Hastings, Berger, Becker, Charnock, Taylor | May 1, 1996 | Done - May, 1996 |
Setup MACS at fourth year sites | Miller, Wertheimer, Franklin, Check, Zinga, Becker, Charnock, Taylor | February, 1997 | Done - April, 1997 |
Setup PCs at fourth year sites | Miller, Wertheimer, Franklin, Check, Zinga, Becker, Charnock, Taylor | March, 1997 | Done - May, 1997 |
User Devices Owned by CMU Donated to PPS | Berger, Huntoon, Wertheimer, Miller, Lentz | March 1, 1997 | Pending |
Responsible Party | Deadline | Task Accomplished | |
trouble@pps.pgh.pa.us | Ed staff, PPS Tech staff | January 1, 1997 | Pending |
Staff Development | Ed staff, ?? | January 1, 1997 | Pending |
resources@pps.pgh.pa.us, info@pps.pgh.pa.us, webmaster, etc. | Ed staff, ?? | January 1, 1997 | Pending |